- 2017 Medowie The Bower Estate, 2km of 250mm Pressure Sewer Rising Main, including Barometric Loop Pit and venting instillation.
- 2017 Raymond Terrace, Rising Main to Potters Lane Estate.
​
Comdain Infrastructure
- 2017/2018 upgrades to Water Main Pump Station at Fennel bay and Toronto as part of the Central Coast Inter Regional Water Transfer Project for Hunter Water.
​
RMS
- 2017/2018 Duffie Drive intersection Upgrade. DICL Water Main Relocation and Cross Connection Works.